The first batch of “coal to electricity” supporting power grid project construction in Shijiazhuang in 2019 will be completed by the end of August.

Recently, with the completion of the new transformer connection work in the “coal to electricity” project in Dongliangzhuang Village, Gaochun County, the State Grid Gaochun County Power Supply Company took the lead in completing the first batch of “coal to electricity” supporting power grid project construction this year. It is expected that the first batch of "coal to electricity" project of State Grid Shijiazhuang Power Supply Company will be completed and put into operation by the end of August.

Shijiazhuang City is one of the pilot cities for clean and warm winter in the northern region. In addition to Xinji City, other counties (cities, districts) will complete the “coal to electricity” task this year. In accordance with the principle of “promoting the whole village and reforming with electricity”, the municipal power supply company will effectively link the construction of the “coal to electricity” supporting power grid with the new round of rural power grid reconstruction and upgrading, and determine the village that will be “coal to electricity”. From the station, the line, the change, from the high voltage to the low voltage, the grid carrying capacity is comprehensively combed, combined with new construction and transformation, avoiding investment inefficiency and redundant construction, effectively improving the rural household capacity, greatly improving the reliability of power supply, comprehensive Meet the "coal to electricity" load demand.

In order to ensure efficient work, Shijiazhuang Power Supply Company carried out a comprehensive survey of 14 counties (cities, districts) and 38 villages “coal-to-electricity” in March, collecting and analyzing the results of household survey data, and actively connecting the city. Charge d'affaires. At the beginning of May, the company successfully completed the first batch of “coal to electricity” this year.

It is reported that in 2019, the "coal-to-electricity" project of the city's power supply company covers 399 rural areas and 119,900 households. It is expected to add 1955 sets and 720,000 kVA of new distribution, and newly build and transform 4,510 volts and below 4,351 kilometers. The “coal to electricity” project will be put into operation at the end of September. Among them, the first batch of "coal to electricity" project involves 13 counties (cities) and 89,725 residents. It is expected that the project will be put into operation at the end of August.

Aster far infrared heating products, national patent technology, high efficiency, energy saving, safety and environmental protection, has passed the national laboratory testing, EU CE certification, RoHS, EMC electromagnetic compatibility testing, exported to Europe, is an ideal electric heating products.

Learn more, please click here: http://www.asterheating.com



Categories

Contact

CONTACT US

Contact: Asterheating

Phone: +86-024-53816768

Email:muxi6800@163.com

Add:No.46 Shendongsi Road, Shenfu New Zone, Liaoning Province,China.

Scan the qr codeClose
the qr code